Increasing awareness and access for many people in a peatland
Do
Site
Magoar-Penvern
Costs
Detailed estimated costs for the pilot project in Magoar:
|
Operations |
Costs |
|
Mechanical works (access, trees cuttings and crushing) |
5603,61 |
|
Boardwalk making and setting up |
36406,35 |
|
Equipment hiring for the works |
1965,51 |
|
Equipment to buy |
1926,74 |
|
Interpretation (entrance sign, brochure and wood posts) |
4231,45 |
|
Sculptor |
1055,00 |
|
Staff (2 people) |
6051,47 |
|
Schools work (scrub clearance, tree cutting, talus restoration, scrapping) |
1621,25 |
|
Budget Total |
€58861,37 |
Expected schedule of work
Use Table 6.1 from Brittany Report (page17)